Wastewater Treatment at the Moores Creek Advanced Water Resource Recovery Facility

Rivanna Waste logo

FOR IMMEDIATE RELEASE
January 25, 2024


Wastewater Treatment at the Moores Creek Advanced Water Resource Recovery Facility


CHARLOTTESVILLE, VA – The Rivanna Water and Sewer Authority (RWSA) is reporting that, despite damage, which occurred in its largest wastewater pumping station on January 9, 2024, the Moores Creek Advanced Water Resource Recovery Facility (MCAWRRF) continues to fully process all of the wastewater received each day. The damaged wastewater pump station normally has a capacity of 53 million gallons per day (mgd). Approximately 6 million gallons of wastewater from the northern areas of the City of Charlottesville and Albemarle County are being conveyed through a temporary pumping system each day and are being treated through the MCAWRRF to meet regulatory standards. An initial temporary pumping system with a capacity of about 10 million gallons per day has been installed to convey normal wastewater flows around the damaged wastewater pumping station to the MCAWRRF. A second temporary pumping system will be completed in the next several weeks with the pumping capacity of up to 50 million gallons of wastewater each day to manage higher flows that are received at the facility during a storm event.

RWSA Executive Director, Bill Mawyer, stated, “Our dedicated team of RWSA staff, contractors and consultants continue to work diligently to maintain our wastewater treatment process as we restore operation of the wastewater pumping station. Unfortunately, it was necessary to discharge untreated wastewater to Moores Creek for one 26-hour period last week to move forward with the restoration of our wastewater treatment pumping station. Since that time, we have not experienced any wastewater system overflows in Riverview Park or Darden Towe Park, although they may be possible during heavy rain events until the completion of the 50 mgd bypass pumping installation. We are making every effort to protect our environment as we repair this essential utility infrastructure and maintain service for the community.”



Media Contact
Betsy Nemeth
Director of Administration & Communications
Rivanna Water & Sewer Authority
434-977-2970 ext. 111
bnemeth@rivanna.org



Facebook Twitter Email

Other News in * City News Alerts *

News Release CPD

CPD Responds to Three Shots Fired Calls in One Week

Posted on: February 26, 2024 | Last Modified on: December 12, 2023
Rivanna Waste logo

Rivanna Pump Station Bypass Pumping System Update

Posted on: February 16, 2024 | Last Modified on: December 12, 2023
Charlottesville Parks and Recreation

Tonsler Park Parking Lot to be Repaved

Posted on: February 15, 2024
National Burn Awareness Week 2024 CFD

CFD Recognizes Burn Awareness Week

Posted on: February 9, 2024
News Release CPD

CPD Recovers Drugs and Weapons in Search Warrant

Posted on: February 2, 2024 | Last Modified on: December 12, 2023
Rivanna Waste logo

Rivanna Pump Station Bypass Pumping System Update

Posted on: February 1, 2024 | Last Modified on: December 12, 2023
Leaf Collection Announcement 23-24

Leaf Collection to Resume

Posted on: January 25, 2024
Rivanna Waste logo

RWSA Water Main Break

Posted on: January 25, 2024 | Last Modified on: December 12, 2023
Phone Icon

City of Charlottesville to Perform System Maintenance on All Phone Services

Posted on: January 24, 2024 | Last Modified on: December 12, 2023
City Council Postponed

City Council Meeting Postponed

Posted on: January 16, 2024
News Release CPD

CPD Makes Arrest in Rivanna Trail Case

Posted on: January 12, 2024
News Release CPD

CPD Seeks Assistance Locating Suspect

Posted on: January 3, 2024
Public Works

Recycle Your Holidays Trees!

Posted on: December 20, 2023
Deputy Chief Joe Phillips

Joe Phillips Promoted to Deputy Fire Chief

Posted on: December 13, 2023
Leaf Collection Announcement 23-24

Leaf Collection has Begun

Posted on: November 1, 2023
Rivanna Waste logo

DRINKING WATER UPDATE

Posted on: September 12, 2023
Charlottesville Parks and Recreation

Tree Planting Planned for November

Posted on: September 1, 2023
Rivanna Waste logo

FREE LOCAL MULCH AT THE IVY MUC

Posted on: August 29, 2023
Logo for Charlottesville Acting on Climate Together

2023 Climate Action Work Plan Posted

Posted on: July 26, 2023
tax time

Taxes Due Monday, June 5, 2023

Posted on: May 30, 2023